Back at the turn of twenty-ten, I set out our  renovation goals for the coming year. Three months later, let’s take a look at how we’re progressing. We have seven spaces on the to-do list this year: foyer, downstairs bathroom, dining room, office, garage, yard and library. Some projects are smaller whilst others are more time (and budget) consuming. Let’s break it down one by one.
Goal 1: Foyer

- Finish drywall on headers – put up sheetrock, then mud, sand, dust, mud, sand, dust [ad infinitum]
- Prime and paint drywall
- Paint other walls 2nd coat
- Install narrow shelving units in wall cavity
Progress: PARTIAL
We have started putting up sheetrock and mudding in some areas, like the header in the left-side living room. We’ve still got to finish putting up the sheetrock on the right-side header, then mud+sand til our hearts’ discontent.

When we removed the the foyer walls and replaced them with headers to open up the space, we were left with two small partial walls either side of the entryway. These are helpful in visually delineating the two living spaces without taking up too much room. But we’re going to be adding more functionality to these puppies in the form of shelving. In each cavity, we’re installing tall, narrow bookshelves for a built-in cabinetry look. The shelves are built and have been placed in the space:

Now we have to sheetrock them in, then eventually trim around the outside for the custom built-in look. Once all the sheetrock has been mudded and sanded, we can prime and paint … well, everything.Â
Goal 2: Downstairs bathroom

- Finish grouting, molding and decorating
Progress: COMPLETE!
Another one down (ok, the first one down), the first one bites the dust! Sing it, Freddie! Tiling, grouting and molding have all been finished. The decor has been … well … decorated. This transformation is so jaw dropping that it needs a separate post. Ok, maybe its more like I took way too many pictures to post here. So, watch this space, the big reveal is coming soon! But for now, here is a teaser photo…

Goal 3: Dining room

- Install trim boxes and chair rail
- Paint walls 2nd coat, paint ceiling
Progress: PARTIAL
Twenty three boxes have been measured, cut and nailed to the wall. That’s 167 feet of trim, and approximately 980 brads nailed in and filled with putty.

Next up? We’ll caulk around the boxes and paint the trim to make them seamlessly blend in with the wall. We’ll paint another coat of the charcoal grey on the upper walls and then finally remove all the painter’s tape (as long as it has been up, it feels like a design feature). The last step will be to put up the chair rail running around the room. Add a few finishing touches (artwork, decorative knick-knacks … oh yeah, floors and replacement windows) and this room will be finished!
Goal 4: Office

- Finish painting walls
- Get  new office furniture to make office space more efficient (and less ugly)
- Move living room furniture to front living spaces
Progress: ALMOST COMPLETE!
This room has had a total makeover. The walls have been painted (thanks Alyssa!), gone is the makeshift desk, the book cases have been replaced, and all the junk necessary office items seen in the picture above have been organized and housed in more efficient and appealing furniture. The big reveal is coming soon, but for now here’s a teaser pic…

Goal 5: Garage

- Replace door, rails and opener on remaining two garage doors
- Tidy up and organize garage
Progress: NOT STARTED
This is one of two projects we haven’t made a start on yet. With all the renovation projects going on in the house, the garage serves mainly as our storage space/work area and unfortunately will probably be one the last spaces to receive attention.
Goal 6: Yard

- Clear brush from back section
- Fence in rest of yard
Progress: PARTIAL
Rick has made some progress clearing out that dense brush area at the back of the yard. He has cut down several small trees and piled the wood into neat piles:

We still need to work on clearing some of the bigger trees before we can clear out the smaller greenery and brush. But we’re getting there!
Goal 7: Bedroom-turned-library

- Finish header – install last supports, remove studs
- Finish drywall – put up sheetrock, then mud, sand, dust, mud, sand, dust [ad infinitum]
- Prime and paint drywall
- Paint other walls 2nd coat
- Remove existing railing – replace with new wrought iron railing
Progress: NOT STARTED
This is the second project that we are yet to start working on. We really need to finish the sheetrocking of the foyer walls below before we can install the new railing. With our pack of dogs running around, we need to have some kind of partial boundary in place (whether it is the current stud wall or the new railing) to prevent them from going ker-splat over the edge. So, for now, this project is on the back burner whilst we finish downstairs.
All in all, I think we are making good progress with our renovation goals for 2010. Two projects are complete – the bathroom and office reveals will be posted soon. Three projects are in the works – the foyer, dining room and yard will hopefully be finished shortly. Only two out of the original seven projects are yet to be started, which I think is normal given that our priorities are elsewhere in the house for now. How are you coming along with your resolutions? Are you making good progress or have the goals bit the dust?